Project Technicals

Technical Configuration

Engineering parameters of the Obregad Hydropower Project on the current planning basis.

Planning Basis

Technical Parameters

Detailed hydraulic, civil and equipment dimensions will be finalized through the Detailed Project Report (DPR) and the procurement process.

Generating Units

2 × approximately 4.5 MW

Turbine

Francis configuration

Final selection through DPR

Gross Head

Approximately 88 m

Net Head

78.03 m

Planning basis

Design Discharge

13.46 m³/s

Annual Saleable Energy

51.96 GWh

Planning basis

Evacuation Voltage

33 kV

Evacuation Length

Approximately 8 km

Key Project Facts

Planning / Development Stage
Generating Units
2 × approximately 4.5 MW
Turbine
Francis configuration — final selection through DPR
Gross Head
Approximately 88 m
Net Head (Planning)
78.03 m planning basis
Design Discharge
13.46 m³/s
Annual Saleable Energy
51.96 GWh planning basis
Evacuation Voltage
33 kV
Evacuation Length
Approximately 8 km

Run-of-River Principle

A run-of-river scheme generates electricity from the natural flow of the river. Water is captured at an intake, conveyed to the powerhouse through the waterway system, and returned to the river downstream after passing through the turbine — without large-scale storage.

Detailed hydraulic, civil and equipment dimensions will be finalized through the Detailed Project Report (DPR) and the procurement process. Values above are the current planning basis.