Our Project
Obregad Hydropower Project
9 MW Run-of-River Hydropower Project · Obregad Khola, Patrasi Rural Municipality, Jumla District, Karnali Province, Nepal
Project Overview
A Clean-Energy Development on the Obregad Khola
The Obregad Hydropower Project is a planned 9 MW run-of-river hydropower project on the Obregad Khola in Patrasi Rural Municipality, Jumla District, Karnali Province, Nepal. It is being developed by Western Energy and Ventures Pvt. Ltd.
Run-of-river projects generate electricity from the natural flow of a river without large-scale water storage. Clean water is diverted through an intake, conveyed through a headrace system and returned to the river after passing through the generating units.
The figures shown on this website reflect the current project planning case and will be finalized through the Detailed Project Report (DPR), detailed engineering studies, the survey licence stage, regulatory approvals, procurement and definitive agreements.
9 MW Installed
Two generating units of approximately 4.5 MW each.
Run-of-River
Water returned to the river after generation.

Obregad Hydropower Project
Obregad Khola · Jumla, Karnali Province, Nepal
Key Project Facts
Planning / Development Stage- Location
- Obregad Khola, Patrasi, Jumla, Karnali, Nepal
- Installed Capacity
- 9 MW
- Project Type
- Run-of-River
- Design Discharge
- 13.46 m³/s
- Planning Net Head
- 78.03 m
- Annual Saleable Energy
- 51.96 GWh
- Transmission
- Approx. 8 km, 33 kV
- Target COD
- June 2030
- Total Project Cost
- NPR 190 crore
- Debt
- NPR 133 crore
- Equity
- NPR 57 crore
Project Highlights
Key Characteristics
9 MW Installed Capacity
Two generating units of approximately 4.5 MW each for the planned configuration.
51.96 GWh Annual Saleable Energy
51.96 GWh of annual saleable energy on the current planning basis.
Run-of-River Design
A run-of-river scheme that returns water to the river after generation.
33 kV Evacuation
Approximately 8 km of 33 kV evacuation to the interconnection point.
Explore Further
Project Information
Dive deeper into the project's location, technical configuration and development status.
Location
Obregad Khola, Patrasi Rural Municipality, Jumla District, Karnali Province, Nepal
View LocationTechnical Configuration
Engineering at a Glance
Generating Units
2 × approximately 4.5 MW
Turbine
Francis configuration
Final selection through DPR
Gross Head
Approximately 88 m
Net Head
78.03 m
Planning basis
Design Discharge
13.46 m³/s
Annual Saleable Energy
51.96 GWh
Planning basis
Evacuation Voltage
33 kV
Evacuation Length
Approximately 8 km
Development Roadmap
Planned Development Stages
01Survey Licence
ObtainedSurvey licence stage for the project's investigation and study works.
02DPR & Detailed Studies
In DevelopmentDetailed Project Report, geological, hydrological and engineering studies.
Development-stage priority
03PPA with NEA
TargetPower Purchase Agreement with Nepal Electricity Authority.
Targeted in project plan
04Generation Licence
Pending ApprovalGeneration licence from the relevant regulator following required studies and approvals.
Following required studies and approvals
05Financial Close
PlannedSenior debt, equity completion and lender appraisal.
After PPA, DPR, lender appraisal and equity completion
06Construction & Commissioning
TargetCivil works, electromechanical installation and commissioning.
Target COD June 2030