Western Energy and Ventures Pvt. Ltd.

Project Development

Development Status

Where the Obregad Hydropower Project stands today, and the stages planned ahead.

Status Legend

Planned Development Roadmap

The survey licence for the project has been obtained. Remaining stages are shown in their planned sequence with clear status labels.

Statuses are colour-coded to avoid any ambiguity about work that is completed versus work that is planned, targeted or pending. Completed stages are shown in green; nothing else is presented as completed.

Obtained / Completed
In Development
Planned / Target
Pending / Future
  1. 01Survey Licence

    Obtained

    Survey licence stage for the project's investigation and study works.

  2. 02DPR & Detailed Studies

    In Development

    Detailed Project Report, geological, hydrological and engineering studies.

    Development-stage priority

  3. 03PPA with NEA

    Target

    Power Purchase Agreement with Nepal Electricity Authority.

    Targeted in project plan

  4. 04Generation Licence

    Pending Approval

    Generation licence from the relevant regulator following required studies and approvals.

    Following required studies and approvals

  5. 05Financial Close

    Planned

    Senior debt, equity completion and lender appraisal.

    After PPA, DPR, lender appraisal and equity completion

  6. 06Construction & Commissioning

    Target

    Civil works, electromechanical installation and commissioning.

    Target COD June 2030

The figures shown on this website reflect the current project planning case and will be finalized through the Detailed Project Report (DPR), detailed engineering studies, the survey licence stage, regulatory approvals, procurement and definitive agreements.