Modelled planning-case financial information for the Obregad Hydropower Project.
Modelled Returns
Planning-Case Financial Indicators
Label: Modelled Planning Case. These are modelled planning figures, not guarantees.
Modelled Project IRR
~18.4%
Internal rate of return on the project cash flows.
Modelled Planning CaseModelled Equity IRR
~24.7%
Internal rate of return on equity cash flows.
Modelled Planning CaseFinancial projections are subject to detailed studies, approvals, financing arrangements, definitive agreements and actual project performance. These are modelled planning-case figures, not guarantees of return.
Project Cost
Project Cost Breakdown
Planning allocation of the NPR 190 crore total project cost. This is a planning allocation, not a DPR bill of quantities.
Donut Chart
NPR 190 crTotal Project Cost
Bar Chart
Planning allocation on the current base case. This is not a DPR bill of quantities; figures may change following detailed studies, approvals, financing arrangements and definitive agreements.
Summary
Planned Capital Structure at a Glance
Total Project Cost
NPR 190 crore
Senior Debt Target
NPR 133 crore · 70%
Total Equity
NPR 57 crore · 30%
Target COD
June 2030